Laying waste pipes in a renovation before the floor is strengthened

In a renovation we prepared and laid the waste pipes on the floor slab before the strengthening screed was poured.

Where
Milan
When
2018
Systems involved
plumbing · drainage
Frame for a wall-hung toilet with waste pipes on the reinforcing mesh

What needed doing

The waste pipes had to go in before the structural strengthening of the slab, which would cover them.

What we did

We set out the routes and laid the waste pipes within the reinforcing mesh, with frames for the wall-hung fittings and the connections.

The result

When the strengthening screed was poured, the waste pipes were already in and connected.

The service

Photos from the job

  • Waste pipes along the wall, between the floor beams
  • Waste pipes and junctions seen from above
  • Frame with water connections and waste
  • Waste fittings in a corner
  • Old floor wastes before the work
  • Wall-hung toilet frame fixed to the wall
  • Waste pipe through the wall above the reinforcing mesh
  • Waste pipes along the corridor within the reinforcing mesh
  • Waste junctions and bends between the beams
  • Toilet frame with connections before the pour
  • Frames and waste pipes in a bathroom under construction